Should Every Issue Have a Start Date and an End Date?

Forcing start and end dates on every issue puts commitments on the calendar that nobody made. How to tell apart a bug that only has a deadline, a review that needs a date range, and a start that the status history already records.

John Baek
John Baek
Founder, CollabOps
2 min read

A bug comes in Monday morning: attach two or more files to an application and the last filename gets truncated. It has to be fixed before Wednesday's 5 p.m. review. The assignee plans to reproduce it first, then decide whether to start today or tomorrow. But the issue form requires both a start date and an end date. So they put in today as the start. At that moment the calendar shows a Monday start that nobody committed to.

The date fields on an issue should depend on what kind of work it is. Force a start date on work that only has a deadline, and the calendar starts showing promises nobody made.

One team's calendar holds dates that mean different things. (The cases are illustrative.)

WorkWhat we know nowWhat the calendar should show
Fix the attachment bugA fixed build is needed by Wednesday 5 p.m.One deadline marker on Wednesday
User acceptance review of the new intake screenThe business team blocked out Monday through ThursdayA review period from Monday to Thursday
Clean up the permission listThe assignee moved it to In progress Tuesday at 11:20Record the start time in the issue history; show it when viewing work history

Which issues need which dates?

A bug needs one deadline. The acceptance review needs both ends, because a room and reviewers are booked for four days. For the permission cleanup, the system already knows when the status changed. There's no reason for someone to type the same fact into a date field. What the status change tells you, though, is only when the start was recorded. Actual hours spent need a separate log.

How should the screen behave when plans change?

The UI should follow the same distinction. If the program owner pushes the review back a day, the planned bar moves. If a developer picks up the Wednesday bug on Tuesday, the calendar shows the Wednesday deadline and the issue history shows the Tuesday start. Improvement requests with no date yet can live in the backlog with just a priority. Letting teams choose which fields act as start and target dates on a roadmap is also how GitHub Projects' roadmap layout works.

A question to ask once the calendar is in place

At Friday's meeting, ask: "Next Wednesday, do we need people, or do we need a deliverable?" When the review period and the delivery deadline look different on the calendar, both teams can read the same calendar and prepare for what they actually need.

Once deadlines and date ranges are separated, the next thing to see is why a schedule slips. How a delay spreads to other work is covered in Subtasks, related issues and blockers in one release.