Nine of Ten Issues Are Done. Is the Milestone 90% Done?
A 90% completion rate counted by issues can be accurate and still say nothing about whether you can launch. Comparing two projects, we show how to put launch readiness, the blocking issue and the next check time on the milestone card.
A new online application window is set to open Friday at 2 p.m. The morning status update is short: "Nine of ten items done, 90% complete." The program owner wants to know one thing. Can we send the "applications are open" notice at 2 p.m.?
A completion rate counted by issues tells you how much work is finished. Whether you can open the service depends on whether the remaining issue is a launch condition.
Open the last issue in each of two projects. (The projects and numbers are illustrative.)
| Project A | Project B | |
|---|---|---|
| Issues completed | 9 of 10 | 9 of 10 |
| The one left | Production approval for external identity verification | Replacing sample images in the help page |
| Launch condition | Real applicants can only sign in after approval | Intake testing is signed off; the image swap was agreed for after launch |
| Friday's decision | Hold the notice | Send the notice as planned |
Both are at 90%, so why do the decisions differ?
Because the remaining issue blocks launch in one project and not in the other. Both boards are right about 90%, as long as every issue carries the same weight. But in A, nine finished issues still let zero applicants in. In B, the owner of the last item can come back next week and the window still opens today. Why complaints about existing issue trackers usually come down to not finding this kind of answer is covered in The customer said they hate Jira. Do they need a new Jira?
What belongs next to the percentage on a milestone card?
Next to the percentage, write three things: whether launch is possible, which issue is blocking it, and when the next check happens. For A, that's "Launch on hold · waiting on identity verification approval · next check Monday 10:00." Monday at 10 is when the integration owner will check the approval status again. Write that time down as the launch date by mistake and the program owner ends up rewriting the same notice on Monday morning.
For B, "Ready to launch · help image swap planned for next Tuesday" is enough. You can see who owns what's left, and you can see today's decision. To get there, the team has to agree on something when the milestone is created: which items must be done before the service opens, and which can be finished after.
Test it on a real release before adopting it
The CollabOps project view brings issues, milestones and progress together (milestone progress docs). When you evaluate it, pick one real release. Check whether you can read, right next to the percentage, the issue blocking today's decision and the next check time. That tells you which question your weekly report will stop having to ask.