Source Control and Deployment Bought Separately: Who Tests the Integration?
When an agency contracts source control and deployment separately, both vendors can report success while the approved commit and the production file differ. The evidence and checker at each of three handoff points, a timing-based integration test, and what each role signs.
The source-control vendor reports: "the approved commit was delivered correctly." The deployment vendor reports: "the file we received was deployed correctly." Both reports can be true and one question still stands. Did the file built from that approved commit reach production?
When a project is procured in pieces, what needs acceptance testing is not each system but the handoff where they meet. Whether the approved commit, the build input and the production file all point to the same change shows up on neither vendor's screen.
When can handoff conditions be set in split procurement?
In Korean public software projects, whether commercial software must be purchased directly (separately from the integration contract) is decided under Article 54(2) of the Software Promotion Act (소프트웨어 진흥법) and the related notices. When source control and deployment are contracted separately, the agency can define, at the procurement stage, the handoff conditions where the two contracts meet and who owns the integration test. Below is one setup where the agency names the final reviewer and both vendors plus the operations contractor take part. (Change and build numbers are illustrative.)
| Handoff | Evidence from the handing side | What the receiving side checks itself |
|---|---|---|
| Repository → build | Source-control vendor presents change request CR-527 and the approved commit | Deployment vendor checks the actual source revision of build #214 |
| Build → deploy | Deployment vendor presents the artifact digest and test results for #214 | Operations checks it against the approved file and environment |
| Deploy → production | Deployment vendor submits per-server execution results | Operations confirms the real version on both servers and a business request result |
Which test case makes the gap visible?
Use timing. Right after commit A is approved, push change B to the same branch, then run the deployment for A. If the approval record says A but the build read the branch head at run time and picked up B, every individual system screen can still show Success. The integration review catches it at the first handoff condition: approved commit of CR-527 = input commit of #214. Walking back from a production file to its change request, from an auditor's angle, is covered the same way in auditing one production release at a Korean bank.
t0 commit A approved (CR-527)
t1 commit B pushed to the same branch
t2 "deploy A" runs ─▶ build reads branch head, input = B
SCM screen: success / deploy screen: success
integration review: approved commit (A) ≠ build input (B) ─▶ fails at handoff 1Who signs what?
Each role signs for what it can see. The source-control vendor confirms the identifier of the approved source. The deployment vendor confirms the file built from that source and the execution history. The operations contractor confirms what was observed on the targets. The agency's designated inspector checks that all three records point to the same change and decides acceptance under the contract's procedure.
With this structure, a defect doesn't end in "the two vendors need to discuss it." If the build input differs, retest from the first handoff. If the approved and executed files differ, from the second. If the execution report and the production state disagree, from the third.