Designing a PoC Sample Project When Production Source Can't Leave the Agency
Even when real source code and citizen data can't be moved into a test environment, the deployment procedure can still be verified. A synthetic civil-application lookup service, one WAR and two test application servers reproduce approval, cross-network transfer, rolling deployment and recovery, with the remaining checks written into the PoC report.
"We can't move real source code or citizen data into a test environment. Can you still verify our deployment process?" Yes. Reproduce the approvers, the path files travel, the production targets and the recovery decisions as they really are. Without any production data, you can still fully test who approved what, and which server it landed on.
What a deployment PoC must reproduce is the production path, not the production source. If approval, cross-network transfer, server rollout and recovery decisions match reality, the source can be a one-line sample.
How do you build the sample project?
Build one synthetic service, say a civil-application lookup. The sample record is DEMO-001 and the change is "add the expected processing date to the receipt." Package the app as a WAR, the same format the agency's real systems use, and put two web application servers (WAS) in the test production network. The business logic in that one-line change is tiny. The path the release has to travel is built all the way through.
| Condition to reproduce | How the sample tests it | Result that shows it passed |
|---|---|---|
| Approval | A maintenance role submits the change; an agency role approves the target file and environment | Zero production runs before approval; the tested file's identifier visible in the approval history |
| Cross-network transfer | Hand the WAR built on the dev network through the agency's permitted test relay | File digest matches before and after transfer |
| VM and WAS rollout | Apply to the two test servers in sequence and look up the receipt on each | Same version and processing date on both servers |
| Failure and recovery | Have one server fail its readiness check | Rollout stops before the next target; after the agreed recovery, the old screen loads correctly |
[dev network] change submitted ─▶ agency approval (file and environment fixed)
└─▶ WAR (digest d1) ─▶ test relay ─▶ [test production network] digest d1 confirmed
├─▶ WAS 1 apply ─▶ receipt lookup
└─▶ WAS 2 apply ─▶ receipt lookupWhat belongs in the PoC report?
The report should also say what still needs checking in the main project, and with whom. If approval was verified on a test approval screen, integration with the agency's electronic approval system, including rejection and cancellation notices, is still to be tested. If rolling deployment passed on test WAS instances, session persistence on the production middleware, cutover time under real load and the permissions of a service account going through the server access-control gateway must be confirmed in the real environment. Injecting deliberate failures into the same sample is covered in three failures to stage on purpose in a deployment automation PoC, and AI PoCs without a GPU in running a PoC without a GPU.
What sentence should the purchase review get?
A purchase review needs one sentence that states what was shown and what acceptance remains: "Without exporting production source, we verified cross-network delivery of the approved build and rollout and recovery on two WAS instances. Before the main project, electronic approval integration and production session cutover will be added to acceptance testing." Both sides read the same meaning into what was demonstrated and what becomes an acceptance condition of the next contract.