After General TIPS: How to Line Up Research Wrap-Up With a Customer Pilot
The research end date, the day the customer reviews pilot results and the day the official completion ruling arrives are three different dates. A schedule, starting eight weeks out, for teams weighing the TIPS deep-tech follow-on track or Scale-up TIPS.
The research team ran its final experiment on Friday. The earliest date you can get onto the customer's test network is three weeks out. The TIPS operator (the accelerator that recommends startups into Korea's government-matched TIPS R&D program) wants evidence for a follow-on project at the next meeting. If all three calendars just say "research wrap-up," nobody can see who gets to see which result, and when.
Start by splitting the dates. The research end date in the agreement, the day the customer reviews the pilot results, and the day the official completion ruling from the program agency is confirmed. The day your team finishes its evaluation and the day you meet the eligibility requirements for the next program can be weeks apart.
For a team preparing the next step after TIPS, "research wrap-up" isn't one date. Writing down the agreement end, customer pilot review and official completion ruling separately is what keeps the next application and the pilot results pointing at the same evidence.
What needs checking separately for each follow-on path?
The revised March 2026 notice we checked for the General TIPS deep-tech follow-on track (일반 TIPS 후속 딥테크트랙) listed requirements such as an official "completed" ruling for the general track and follow-on investment recognized after the agreement was signed (KRW 500 million or more under that notice). There was an operator recommendation step as well. The same year, Scale-up TIPS (스케일업 팁스) was announced as a separate R&D program linked to investment and loans, with its own investment requirements from Scale-up TIPS operators.
If you're weighing both paths, cross-check the investor and investment date, the completion ruling document, and the application type you're targeting, each on its own. Notices change from round to round, so confirm the details against the original notice when you apply. It's also safer to put a specific "check the notice for that round" date into next year's plan.
How should you use the eight weeks before research ends?
So what can a team schedule right now? Suppose you're building software that links deployments to incidents (the case and counts are illustrative). T below is the week the research is scheduled to end under the agreement.
| When | What the research team leaves | What to settle with the pilot partner |
|---|---|---|
| T−8 weeks | 20 incident cases for evaluation, the answer key, the baseline method and code version to compare against | Which data can be used, the date of test network access, which operations role will review results |
| T−4 weeks | A record of another engineer rerunning the evaluation on the same inputs, with the cases where answers changed and why | The screens operators will see, time measured per task, the form for recording successes and failures |
| T−2 weeks | Whether the version brought into the pilot matches the version that was evaluated | Operators find the relevant deploy with both the new and old methods and record time taken and evidence |
| Week T and after | Final results, how to reproduce them, remaining technical problems. Record the official ruling on the date you're notified | Write the verified scope and exceptions into the results report, then agree on the next target and who will verify it |
What do the researcher and the customer each want from the same pilot?
The researcher's question is "in how many of the 20 cases did we find the deploy we defined as correct?" The customer's question is "can an on-shift operator look at this evidence and choose what to check next on their own?" To get both answers from one pilot, go beyond a single screenshot and record which input, on which version, produced which evidence, and what the operator did next.
That record gets written up differently for each path. A deep-tech research plan can include the technical problems you didn't solve and the next experiments. A scale-up conversation can show how far you've validated in a customer environment and what cost and work the next site install will take. And the pilot partner ends up with something better than "the product worked": a result that helps them make their next decision. The material I built up before the first TIPS application is in four things to have ready before applying to TIPS.